Effect of Aluminum Formwork on Construction Cost and Quality

BOFU plastic formwork system

The proportion of the formwork in the construction cost is not large, but it is the most space-saving and cost-effective turnover material. Sometimes it is really a choice that the cost of formwork in a building is 50,000 or 100,000. I hope that the author’s experience can help to see the development, construction, and labor companies of this article, improve quality, reduce costs, take less detours, and build more projects.

0001
First of all, starting from the aluminum formwork, after all, the aluminum concrete forms is now hot, and there are many friends concerned.
The aluminum formwork replaces the traditional formwork, square wood, and steel pipe, which is equivalent to the formwork + support system. This product does not appear in China for a long time. The first aluminum mold project I saw was about 2012, and it developed only 7 years to now, but the development is very fast. Now in the domestic construction industry, although only some projects are used, basic everyone has heard of it and has some understanding, which shows that it does have outstanding features.

0003
The following are some of the advantages and disadvantages of the aluminum formwork collected by the author through interviews with users, etc., for the reference of interested friends.
Advantages:
1. Industrial standard production, the quality is relatively stable.
2, precise determination, high bearing capacity, relatively stable concrete forming.
3. Skillful workers have high construction efficiency.
4, can be equipped with a quick release system, less on-site garbage.
5, the number of turnover is high, can be recycled and refurbished.

Disadvantages:
1. The cost is high, and the one-time investment is large. Even if it is rented, the cost is high.
2, after the deformation is difficult to repair, repair trouble, generally a small deformation will lead to a large piece affected.
3. workers must have corresponding construction techniques, otherwise the efficiency is low and the effect is poor.
4, aluminum alloy surface and concrete are prone to oxidative corrosion, resulting in bubbles affecting concrete molding.
5. the energy consumption of electrolytic aluminum production is large, and oily release agent is required for use.

Aluminum formwork have been in Europe and the United States for more than 50 years and have long-lasting vitality. Most of the domestic aluminum mold technology originates from Germany’s PERI and Austria’s DOKA. Like countless materials, aluminum formwork currently have significant advantages and disadvantages (because of the unknown reason, the market share in Europe and the United States seems to remain low. From the annual plywood export data in China, the construction industry in Europe and the United States is still in heavy use. Wood glue board). In the process of domestic development, many outstanding talents are constantly improving it to make it more suitable for the current construction situation in China.

0002
On the whole, the current aluminum formwork is improved under the correct construction technology, and the cost is increased. For example, build a single floor area of 700 square meters, about 30 floors of high-rise residential standard floor, the rental fee is about USD250,000. Under the condition of the new plastic formwork, according to the scheme used by the author’s customer, the standard layer formwork of the same building can be completed within USD200,000, and the formwork still can use around 70 times!
I hope that the talents of construction engineers can make the aluminum formwork more cost-effective. How far this product can go, and wait for time to test.

The proportion of the formwork in the construction cost is not large, but it is the most space-saving and cost-effective turnover material.Sometimes it is really a choice that the cost of formwork in a building is 50,000 or 100,000.I hope that the author’s experience can help to see the development, construction, and labor companies of this article, improve quality, reduce costs, take less detours, and build more projects. 0001 First of all, starting from the aluminum formwork, after all, the aluminum concrete forms is now hot, and there are many friends concerned. The aluminum formwork replaces the traditional formwork, square wood, and steel pipe, which is equivalent to the formwork + support system.This product does not appear in China for a long time.The first aluminum mold project I saw was about 2012, and it developed only 7 years to now, but the development is very fast.Now in the domestic construction industry, although only some projects are used, basic everyone has heard of it and has some understanding, which shows that it does have outstanding features. 0003 The following are some of the advantages and disadvantages of the aluminum formwork collected by the author through interviews with users, etc., for the reference of interested friends. Advantages: 1. Industrial standard production, the quality is relatively stable. 2, precise determination, high bearing capacity, relatively stable concrete forming. 3. Skillful workers have high construction efficiency. 4, can be equipped with a quick release system, less on-site garbage. 5, the number of turnover is high, can be recycled and refurbished. Disadvantages:
模板在建筑成本中所占的比例并不大,但它是最节省空间和最具成本效益的周转材料。有时,建筑物中的模板成本实际上是50,000或100,000。我希望作者的经验可以帮助我们了解本文的开发,建设和劳务公司,提高质量,降低成本,减少走弯路,并建立更多项目。

0001
首先,从铝模板开始,毕竟铝混凝土形式现在很热,有很多朋友关注。

铝模板取代了传统的模板,方木和钢管,相当于模板+支撑系统。该产品长期不在中国出现。我看到的第一个铝模具项目大约是2012年,它发展到现在只有7年,但发展非常快。现在在国内建筑行业,虽然只使用了一些项目,但基本上每个人都听说过它并且有一些了解,这表明它确实具有突出的特点。

0003
以下是作者通过采访用户等收集的铝模板的一些优缺点,供感兴趣的朋友参考。

好处:
1.工业标准生产,质量相对稳定。
2,精确测定,承载力高,混凝土成型相对稳定。
熟练的工人具有很高的施工效率。
4,可配备快速释放系统,减少现场垃圾。
5,营业额高,可以回收和翻新。

缺点:

BOFU plastic formwork system